Demonstration Environment — Fictional Data
Execution Roadmap

Initiative INI-102 · Player Development

Athlete Development Tracking System

No longitudinal data on athlete growth to guide coaching decisions.

At Risk
Progress vs plan
48% / 70% planned
Accountable owner
Dana WhitfieldAthletic Director · Athletics
Timeline
2025-Q2 → 2026-Q4Phase: Build
Resources
Vendor platform, data coordinator

Advances objective 1.1

Build a unified K–12 athlete pathway

Budget

Financial requirements

Approved budget
$60,000
Spent to date
$38,000
Remaining
$22,000

63% of budget consumed at 48% completion — spend running ahead of delivery.

Funding sources

  • Regional Sports FoundationProspect

Delivery

Milestones

  1. Vendor selected

    Completed

    Due Nov 30, 2025 · completed Jan 20, 2026

  2. Baseline assessments loaded

    Overdue

    Due Sep 30, 2026

Linked KPI

Feeder athletes advancing to varsity

Watch

Current 57 · FY2026 target to date 63.7 · Annual